Western Grandstand — 800t Structural Steel

800t
Structural Steel — Roof
5,000+
Steel Items Managed
8 Months
Project Duration
01
Engaged
GC21
Contract awarded
02
Mobilised
Parramatta
On-site delivery
03
Delivered
8 Months
Total programme
04
Outcome
Zero Harm
Safety standard met
Project Summary

Western Grandstand — 800t Structural Steel

AJM United were engaged by Lend Lease under a GC21 contract to construct the western grandstand roof at Western Sydney Stadium — one of NSW's most iconic new sporting venues. The roof alone consisted of approximately 800 tonnes of structural steel.

Key Achievements

Milestones engineered into delivery.

Quantifiable wins from a programme delivered to the highest engineering, safety and environmental standards.

800t
Structural Steel — Roof
5,000+
Steel Items Managed
8 Months
Project Duration
Specialist Building Industry
Sector-specific expertise applied end-to-end
01 — Challenge

The Challenge.

The painting of two different AKZO Nobel paint systems required a stringent identification and traceability tagging system and around-the-clock shifts to meet the project schedule. Managing over 5,000 steel items — all connections being splice joints and friction type — demanded a streamlined system for incoming material organisation, separation, and prioritisation in coordination with Southern Steel supplier.

Western Sydney Stadium — on-site delivery
On-site · Parramatta
In The Field

Project Gallery.

A visual window into the building sector environments AJM United operates within.

Western Sydney Stadium structural steel
Western Sydney Stadium structural steel
Heavy fabrication for buildings
Heavy fabrication for buildings
Building site construction
Building site construction
Structural engineering detail
Structural engineering detail
04 — Outcome

Delivered. Safely. On time.

All project milestone dates achieved. NSW Government inspector praised AJM United's overall quality; feedback to Lend Lease was outstanding. Zero rework. The project remains a benchmark for AJM United's capability in complex building infrastructure.

Ready to discuss your project?